Țuca Zbârcea & Asociații law firm wins an arbitral dispute worth EUR 5.5 million

An irrevocable ruling handed down by the supreme court in a EUR 5.5 million arbitration ends a nine-year-long dispute whereas Țuca Zbârcea & Asociații represented a private company for an arbitral dispute worth EUR 5.5 million. 

The dispute arose from a contract concluded in 2007. Under such contract, a private company had undertaken obligations to design, deliver, install and train the beneficiary's staff in connection with the performance of an electronic archiving system.

Given that its contractual partner (a public authority) refused to pay the second instalment of the agreed price, the company initiated in 2012 an arbitral dispute before the International Commercial Arbitration Court of the Chamber of Commerce and Industry of Romania. 

Initially, by an arbitral award handed down in 2015, the arbitral tribunal admitted the claims consisting in the price balance, and it forced the public authority to pay approximately EUR 5.5 million. Next, in 2016, the Bucharest Court of Appeal admitted the action for annulment filed by the public authority and annulled the arbitral award, retaining that the dispute could not be subject to arbitration. Finally, the company lodged a final appeal against such ruling before the High Court of Cassation and Justice and this month, the supreme court handed down its irrevocable ruling whereby it allowed the company's final appeal and thus it maintained the initial arbitral award.

This closes a real saga arising from this contract. At the end of 2019, the supreme court previously handed down a final ruling in yet another dispute between the same parties, whereas the company had requested the refund of the amount of the letter of bank guarantee abusively enforced by the beneficiary. At that time, the High Court of Cassation and Justice rejected the authority's final appeal and thus it maintained the arbitral award under which the authority had been obliged to pay an amount of approximately EUR 1.4 million.

The case involved a variety of legal reviews, debates on issues such as international contract law and the effects of Romania’s commitments towards the European Commission, the limits of arbitrability from the perspective of general and special procedural rules, the delimitations between various types of contracts entered into with the public authorities on the basis of general or special rules, the application of the principles of contractual liability in a complex relationship, both from the perspective of the obligations assumed by the parties and from the perspective of the way in which such relationship evolved.

The ruling of the supreme court contributes to the consolidation of arbitration as a viable alternative for the relief of the courts and to the observance of the principle of the binding force of the contracts between private companies and public authorities.

In this dispute, the applicant was represented by a legal team coordinated by Cornel Popa and Ioana Gelepu, Partners in the Litigation and Arbitration practice group of Țuca Zbârcea & Asociații, as well as Cornelia Tăbîrță, Managing Associate within the same department. 

June 19, 2024 08:09
The case was settled by a recent decision of the High Court of Cassation and J...more »
April 17, 2024 16:26
Schoenherr Romania successfully assisted Societatea Energetica Electrica (Elec...more »
 
April 01, 2024 16:01
Țuca Zbârcea & Asociații has obtained the first final ruling of the H...more »
November 29, 2023 13:46
Zamfirescu Racoți Vasile & Partners (ZRVP) has obtained in court the annu...more »
*
Govnet Next Events